Transportation by sea of monopiles for offshore wind farms. Commissioned by Conbit Engineering, Holmatro supplied a seafastening system.
Commissioned by: Conbit Engineering
Location: United Kingdom
Situation
For the installation of offshore wind farms, the components, including monopiles (hereinafter: MP’s) are transported by sea on specially constructed heavy-lift vessels.
Challenge
Conbit Engineering in Best, Holland, designed the so-called seafastening construction for the UK installation company Seajacks that ensure that the MPs remain securely in position, even in the most extreme circumstances. The MPs (weight: 600 ton p/pcs) rest on two support points and are secured to the deck with straps with the aid of a saddle construction. Four straps, each with a pre-stressed capacity of a minimum of 50 tons, must be anchored to each support point. The pre-stressing is ensured with the aid of an auxiliary construction with 2 large stud ends.
Solution
Holmatro supplied the pulling cylinders, each with a capacity of 60 tons, for this purpose. In view of the fact that cylinders remain in the construction for a long period of time, they have been made resistant to the conditions at sea. They are also fitted with special couplings that are suitable for offshore applications.