Moving a tunnel

 

Moving a tunnel

The new Helperzoomtunnel is now in the right place. The operation took about three hours. A tunnel weighing 6,000 tonnes was moved 45 meters to its final location. Holmatro supplied 40 new cylinders at the behest of the general contractor Civiele technieken deBoer.

Read more about this product

Commissioned by: Civiele technieken deBoer
Location: Helperzoomtunnel, Groningen, the Netherlands

Situation

A new roadway had to be placed under the railway tracks between the Helperzoom and the Europapark: the Helperzoomtunnel. This new connection changes traffic flows in the Helpman and Coendersborg districts. A traffic plan was drawn up to ensure these districts remained liveable and the traffic situation remained safe

Challenge

The Aanpak Ring Zuid project was started in 2017. A part of this project is the new Helperzoomtunnel. In August 2019, this 6,000-ton tunnel was taken out of service and moved 45 meters to its final location.

Solution

To move this 6,000-tonnes tunnel required Ct deBoer to initially install 40 new cylinders from Holmatro together with 32 of its proven predecessors. The HJ150S20SN-HD is the new type of hydraulic jack used. This jack can handle a 10% shear force and is equipped with screw thread Tr160*12. Ct deBoer opted to finish the new jack with a Duplex (Nickel/Chrome) cylinder housing.

Watch the time-lapse video made by the Combinatie Herepoort and the Aanpak Ring Zuid about the relocation of the Helperzoomtunnel:

Would you like to know more about this project? Contact us via e-mail [email protected] or call +31 (0)162 751500.